structbureau
Structural
- Oct 25, 2012
- 8
Hey,
I am having an issue with typical temporary movement joint detailing using horizontal dowel's grouted after 56 days in my PT-flat plate slab.
The situation:
I am trying to isolate lift/stair well core walls and a shear wall using horizontal dowel connections. They are located 35 m away from each other however the shear wall runs perpendicular to the core's.
The builder and consultant want to use 170mm slabs with 8.3m spans (however not allowed by current codes but they have a tech gliche in there DA) so P/A is quite high to control deflections etc varying b/w 2-2.5 P/A....
The rest of the perimeter is isolated by a building movement Joint...
The question:
In theory the TMJ detail works, however how do you ensure that onsite workers install the horizontal dowel joint system properly and centre the reinforced bars to the PVC piping provided?
.. i.e. normally they will just sit the PVC piping on the bars and it would not be central (gravity). I wouldn't worry about this normally but because of the high P/A shortening of the slab will be quite significant, 170mm deep flat plate will crack quite easily when restrained.
I'd like to hear your technique / system you use for correct installation..
Regards
Bill Mason