IJR
Structural
- Dec 23, 2000
- 774
What is the minimum wind load used to check erection time conditions?
Or where is this issue well covered?
Assume you have to erect a long span truss on temporary structure on an open terrain at elevation above 10meters(33ft). Workers will be working on the temporary structure for at least two weeks.
Or where is this issue well covered?
Assume you have to erect a long span truss on temporary structure on an open terrain at elevation above 10meters(33ft). Workers will be working on the temporary structure for at least two weeks.