tab101
Civil/Environmental
- Feb 24, 2014
- 7
Hi all,
I'm working on a construction project with steel pile caps and I've only ever worked with concrete pile caps so I'm a bit unsure of how to deal with this issue.
In terms of vertical tolerance, normally with concrete pile caps, the cap is poured low (eg 50mm below steel base plate), the base plate is precisely set so top of steel is correct and grout is used to make up any deviations.
Here, the design has structural steel being landed directly on steel pile cap. We have one contractor doing the piles & pile caps with various tolerances (say +/- 5mm for top of pile cap elevation for this example) and then another contractor fabricating and erecting the steel, with their own tolerances on both fabrication and finished steel level (say +/- 5mm).
So my concerns are, how should compounding tolerances dealt with? For example, if pile caps are 5mm high but within tolerance, and the steel fabrication is 2mm too long but within tolerance, so the top of steel is 7mm too high, how should this be dealt with? I understand you could, for example, not fabricate until after pile caps have been installed and surveyed, but this isn't an option here. Going forward, we are having the pile caps to be installed slightly lower, as shimming is easier than having to cut and reweld. Aside from the technical issue, assigning responsibility seems commercially problematic.
Anyone have any experience in general around this sort of situation?
Thanks
I'm working on a construction project with steel pile caps and I've only ever worked with concrete pile caps so I'm a bit unsure of how to deal with this issue.
In terms of vertical tolerance, normally with concrete pile caps, the cap is poured low (eg 50mm below steel base plate), the base plate is precisely set so top of steel is correct and grout is used to make up any deviations.
Here, the design has structural steel being landed directly on steel pile cap. We have one contractor doing the piles & pile caps with various tolerances (say +/- 5mm for top of pile cap elevation for this example) and then another contractor fabricating and erecting the steel, with their own tolerances on both fabrication and finished steel level (say +/- 5mm).
So my concerns are, how should compounding tolerances dealt with? For example, if pile caps are 5mm high but within tolerance, and the steel fabrication is 2mm too long but within tolerance, so the top of steel is 7mm too high, how should this be dealt with? I understand you could, for example, not fabricate until after pile caps have been installed and surveyed, but this isn't an option here. Going forward, we are having the pile caps to be installed slightly lower, as shimming is easier than having to cut and reweld. Aside from the technical issue, assigning responsibility seems commercially problematic.
Anyone have any experience in general around this sort of situation?
Thanks