There is no requirement in ASME codes to [highlight #FCE94F] perform field or shop impact test[/highlight] of welding consumables prior to performing production welds.However if the design code calls for impact test then it's always advisable to purchase welding consumables with impact test([highlight #FCE94F]which is to be performed by consumable manufacturers[/highlight]). [highlight #FCE94F]Impact test temperature for the welding consumables should equal or be lower than the PQR impact testing temperature.[/highlight]
ASME codes has a provision of production weld coupons, which is far stringent in European Codes. [highlight #FCE94F]Failures of any production coupons could hold up all the remaining production welds and production schedule.[/highlight] Should such requirements in design contract,then it's [highlight #FCE94F]strongly advisable[/highlight] to procure impact tested welding consumables.
Also if the impact test temperature is too low, say -50 Deg or -75/-100 Deg for C.S and few grades of low alloy steels(say 2.5% or 3.5% Nickel Steel), then its advisable to have consumables impact tested in the [highlight #FCE94F]highest heat input condition, 3G upwards[/highlight] as additional safety.
Thanks.
Pradip Goswami,P.Eng.IWE
Welding & Metallurgical Specialist
Ontario,Canada.
ca.linkedin.com/pub/pradip-goswami/5/985/299
All provided answer are personal opinions or personal judgements only. It's not connected with any employers by any means.