brnt
Civil/Environmental
- May 7, 2010
- 22
I am a site inspector on a project where the contractor wants to be paid for down time due to a delay. The contract clearly states he can be paid for costs for a delay caused by the owner or their representatives. Basically a rough grading contractor ran into some under ground springs and the engineering firm was to come up with a stradegy for dealing with them. The engineering firm hummed and hawed and danced around but didnt come up with an answer for 2 weeks. The contractor did all they could and then had to sit for 7 days waiting for an answer. They parked their equipment and sent their men elsewhere. They have sent a bill for the 7 days the equipment was sitting idle. The hourly rate for the equipment includes an operator, but their operators were not onsite.Should they get paid the full hourly rate or should there be a discount because their operators were not onsite?