Background - I was involved in a PO for a small pipeline and pump station project with a utility contractor. 3/4 through the job, the Owner kicks my utility contractor off the job, and brought in their own people to complete the work. My contractor sought to return parts purchased for the job they now no longer needed to install. All parts were returned for credit, except for 3 individual items that are claimed to be special order. I, as the PM, was unaware these parts were special order, but from my contractors preferred vendor they apparently are (I know my vendor preferred vendor has similar items in stock). Anyway - my contractor is now requesting I reimburse him for parts that 1) were not installed and 2) not returnable. Also, this contract was a lump sum purchase order, but individual line items for components were included the the PO.
I can go into more detail if needed, but do I have a leg to stand on and refuse payment for these parts since I was unaware they were special order?
Thanks in advance for any information or direction you can provide.
I can go into more detail if needed, but do I have a leg to stand on and refuse payment for these parts since I was unaware they were special order?
Thanks in advance for any information or direction you can provide.