MagicFarmer
Structural
- May 2, 2017
- 38
Good afternoon,
I am currently reviewing a construction deficiency and was hoping for some additional guidance. The contractor has installed a heavy W760 that spans ~8.0 m and has introduced a sweep in the top flange of approximately 25-50 mm and has installed the precast concrete floor. This exceeds the Permissible Variation in Straightness limitation of L/1000 in ASTM A6.
With this limitation in mind I am unsure how to proceed without removing the attached floor slab and having the structural steel contractor plumb the beam. Do you have any additional resources or suggestions on how one might proceed?
Thank you,
MF
I am currently reviewing a construction deficiency and was hoping for some additional guidance. The contractor has installed a heavy W760 that spans ~8.0 m and has introduced a sweep in the top flange of approximately 25-50 mm and has installed the precast concrete floor. This exceeds the Permissible Variation in Straightness limitation of L/1000 in ASTM A6.
With this limitation in mind I am unsure how to proceed without removing the attached floor slab and having the structural steel contractor plumb the beam. Do you have any additional resources or suggestions on how one might proceed?
Thank you,
MF