vato
Structural
- Aug 10, 2007
- 133
After the footing rebar inspection I requested the compaction test results since fill was imported (first note on my foundation drawing of course). After the footing was poured the contractor shows me a letter from a PE who couldn't do the compaction test because it was over 30% oversized material. He, the contractor, decided it was ok to build on. The testing occurred a week before my rebar inspection so the contractor knew darn well that I would have put a stop to the pour without testing. Two questions:
1. Is there a reliable method for determining the soil compaction at this point, with footings on the ground and material too large for a cone test? I've seen those nuclear density testers before. Would that be an option?
2. Can I remove myself ethically as EOR based upon the contractor's deception concerning this matter?
I will be discussing this with the building department. It's a small town and they just let my stuff right on through without understanding it I'm afraid.
thanks
1. Is there a reliable method for determining the soil compaction at this point, with footings on the ground and material too large for a cone test? I've seen those nuclear density testers before. Would that be an option?
2. Can I remove myself ethically as EOR based upon the contractor's deception concerning this matter?
I will be discussing this with the building department. It's a small town and they just let my stuff right on through without understanding it I'm afraid.
thanks