Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations SSS148 on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

control joints spacing resource

Status
Not open for further replies.

hippo11

Structural
Mar 21, 2003
161
Where can I read about good rules of thumb for spacing control joints/construction joints in a slab on grade...where, how often, etc?

Thanks.
 
Replies continue below

Recommended for you

The PCA has a publication called "Building Movements and Joints". In it it talks about controls joints for buildings but also has a chapter on plain sog. They provide a table for recommended joint spacing based on slump, aggregate size and slab thickness (t). The rule of thumb provided is 24t for aggregate < 3/4-inch, 30t for aggregate > than 3/4-inch, and 36t for low-slump.

For sog with reinforcement, there is the subgrade-drag-method equation describing the required area of steel to hold the cracks tight.
 
Here are some publications that I use for reference.
After several problems with floor slabs on grade, I don't think that there is anything like a "rule of thumb" for floor slabs.

Metezger/McGuire web site has some helpful information.
There is a publication "Design of Slabs on Grade" [ACI Committee 360R-94].
Guide for Concrete Floor and Slab Construction ACI 302.1R-04
ARMY TM 5.809.12 / AIR FORCE AFM 88-3 chap. 15
 
ACI 360 is now 06. They have updated a lot. 18 feet spacing max. 1.5 to 1 ratio max
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor