Hello All, Newbie here, just want to get some expert advice, with regards to cooling tower replacement.
Do you just get the same specs of the cooling tower and replace it same for same? or you still calculate the heat load of the building to compare to existing?
second, when you change the cooling tower and condenser water pump, are you required also to replace VFD / controls or you can reuse what is there?
Third, for permit documents, do you add the rental cooling tower in the plans or just let the contractor figure it out? would really appreciate some advice. Thank you.
Do you just get the same specs of the cooling tower and replace it same for same? or you still calculate the heat load of the building to compare to existing?
second, when you change the cooling tower and condenser water pump, are you required also to replace VFD / controls or you can reuse what is there?
Third, for permit documents, do you add the rental cooling tower in the plans or just let the contractor figure it out? would really appreciate some advice. Thank you.