Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Corroded piping collaterally detected

Status
Not open for further replies.

Joss10

Mechanical
Dec 27, 2012
108
Dear mates,
Question:

During the evaluation of radiographic welds, the piping base material was observed corroded.
That indication should be evaluated under the provisions of what code.

Any input will be appreciated.
 
Replies continue below

Recommended for you

Depending on the parts which was fabricated under certain Codes, for example, pressure piping under B31.1/31.3 codes, pressure vessel under ASME VIII, tank under API-650, etc. It could be under the visual inspection as required per Code.
Suggest to consult with Material Engineer or perform a failure analysis to understand the root cause.
 
If the piping is in operation, and it is desired to keep it in operation, then API 579-1/2 or BS 7910 is a better bet.

Steve Jones
Corrosion Management Consultant


All answers are personal opinions only and are in no way connected with any employer.
 
For clarification:

Piping system construction is on going all piping and fittings were expected to be brand new.
 
What code are you building the pipe to? That is the answer. Use the acceptance criteria for new pipe, and/or if it refers in the code methodology(s) to assess corrosion (such as ASME B31 or API 579) use this to assess.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor