TPNY
Structural
- Sep 29, 2004
- 80
I ran into an engineer's inspection report written for my company by the only engineering firm in the area that is willing to do reports for condo conversions.
Before I reach my point, I would like to interject the following: the report was written by a very young, inexperienced, green engineer and signed by his boss, the PE, who never visited the site; needless to say, a lot of cracks were identified incorrectly as were the reasons for the cracks developping. The building is an old matress factory that was turned into apartments in the early 70's. Being the only engineer in the company (also the only one in the history of the company) these reports get thrown at me to evaluate when something looks suspicious.
Now the situation... the engineer identified a long crack in the floor slab running about 3-4" from an adjacent beam and going the entire depth of the slab (the slab was poured monolithically with the beams and girders; two-way slab). The crack -obviously -is from shear failure and most likely occurred during the factory-era. His solution (because he doesn't like to see cracks in concrete) is to cut the whole crack out of the floor slab, and re-pour. When I read this, I was floored (no pun intended)! I thought that practicing professional engineers were more competent than this!!! There are about a dozen easier solutions that would actually "fix" the problem (if it's needed- a thorough analysis has not been approved, so I haven't been able to investigate further).
Has anyone else had any problems like this? I hope I'm not the only one... wait a minute... I DO hope I'm the only one!
Before I reach my point, I would like to interject the following: the report was written by a very young, inexperienced, green engineer and signed by his boss, the PE, who never visited the site; needless to say, a lot of cracks were identified incorrectly as were the reasons for the cracks developping. The building is an old matress factory that was turned into apartments in the early 70's. Being the only engineer in the company (also the only one in the history of the company) these reports get thrown at me to evaluate when something looks suspicious.
Now the situation... the engineer identified a long crack in the floor slab running about 3-4" from an adjacent beam and going the entire depth of the slab (the slab was poured monolithically with the beams and girders; two-way slab). The crack -obviously -is from shear failure and most likely occurred during the factory-era. His solution (because he doesn't like to see cracks in concrete) is to cut the whole crack out of the floor slab, and re-pour. When I read this, I was floored (no pun intended)! I thought that practicing professional engineers were more competent than this!!! There are about a dozen easier solutions that would actually "fix" the problem (if it's needed- a thorough analysis has not been approved, so I haven't been able to investigate further).
Has anyone else had any problems like this? I hope I'm not the only one... wait a minute... I DO hope I'm the only one!