haynewp
Structural
- Dec 13, 2000
- 2,306
See attached picture. The footings are all either 5’-6”x5’-6”x1’-6” or 8’-0”x8’-0”x1’-6”. They are all supposed to have #6 at 12” at the top and bottom of the ftgs.
The contractor said they poured these and out of 18 of them, about 5 of them are showing these large cracks less than 24 hours after pouring. He said the rest have some hairline cracking. I don't think he used ANY curing, just poured them in about 60 degree weather and it got down to about 40 degrees that night. Contractor doesn’t know how deep the cracks go yet but said he could insert the edge of a car key down into some of them. The mix they proposed is below. I was thinking heat of hydration made worse by no curing but I didn't see a very high cement ratio when I went back to the mix. They want to inject an epoxy down into the cracks to restore the capacity. I am concerned about the amount of time to wait before they inject the epoxy and if the epoxy can get down far enough into the cracks. I am also concerned the #6 bars got installed in the top of the footings if this much cracking occurred.
Cement C-150, Type 1/2: 400 lbs
Type C Ash: 100 lbs
#57 Stone: 1843 lbs
MFG Sand: 1128 lbs
NAT Sand: 268 lbs
Water: 275 lbs
Air: 6%+/- 1.5%
Slump: 3 to 5 in
Sand/Agg: 0.43%
Sand FM: 3.01%
5.32 bags
water/(c+p): 0.55
The contractor said they poured these and out of 18 of them, about 5 of them are showing these large cracks less than 24 hours after pouring. He said the rest have some hairline cracking. I don't think he used ANY curing, just poured them in about 60 degree weather and it got down to about 40 degrees that night. Contractor doesn’t know how deep the cracks go yet but said he could insert the edge of a car key down into some of them. The mix they proposed is below. I was thinking heat of hydration made worse by no curing but I didn't see a very high cement ratio when I went back to the mix. They want to inject an epoxy down into the cracks to restore the capacity. I am concerned about the amount of time to wait before they inject the epoxy and if the epoxy can get down far enough into the cracks. I am also concerned the #6 bars got installed in the top of the footings if this much cracking occurred.
Cement C-150, Type 1/2: 400 lbs
Type C Ash: 100 lbs
#57 Stone: 1843 lbs
MFG Sand: 1128 lbs
NAT Sand: 268 lbs
Water: 275 lbs
Air: 6%+/- 1.5%
Slump: 3 to 5 in
Sand/Agg: 0.43%
Sand FM: 3.01%
5.32 bags
water/(c+p): 0.55