Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations GregLocock on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Crane Runway Beam Reinforcement 2

Status
Not open for further replies.

DG-Design

Structural
Jul 27, 2023
2
Hello.

I am currently reviewing the design of an existing top-running bridge crane. The owner would like to increase the capacity of the crane and wants to verify the existing runway beams can handle the increased load. The existing runway beam is a 24WF100 (structure was built in the 50s) with a C15x33.9 cap. The beam span is 18 ft between column centers.

When I perform my design checks, the interaction equation for biaxial bending yields a U.C. of 0.94. Bending about the X-X axis contributes 0.77 and bending about the Y-Y axis is 0.17 of said interaction equation. The owner would prefer that the U.C. be less than or equal to 85% of design capacity for extra safety.

I've researched several ways to reinforce the current beam, but I would like to see if there are some things I have not considered. Intermediate stiffeners are not the most effective for moving loads, have significant fatigue concerns, and AISC DG7 references Tech Report 13 which says these stiffener welds need to be full pen. I would not like to go that route. Since AISC DG7 mentions that a better practice is to thicken the web so that stiffeners are not required, my thought was to add a web plate to the beams to essentially double the current web (doubler plates). This would obviously increase the MoI and section modulus which would reduce the X-X axis bending moment contribution to the interaction equation.

With (4) end truck wheels on each side of the bridge, the max moment, according to my calcs, occurs at 9.27 ft along the beam span. I was thinking about adding a web plate to roughly 8 ft of the center of the beam since your bending moment decreases as you get closer to the supports. Does this seem reasonable to get my U.C. at or below 0.85? Also, I would greatly appreciate weld considerations if this is a viable option.

Thank you in advance.
 
Replies continue below

Recommended for you

My thought would be to add a plate or a member below the bottom flange. This will increase stiffness and moment capacity a lot faster than a web plate.

DaveAtkins
 
Sounds like a viable option to me. Welds should be continuous, rather than intermittent. Did you check sidesway buckling?

If the tension flange is reinforced, you may still end up having a UC higher than 0.85 at the compression flange. Just something to check.
 
@DaveAtkins
Thank you for the advice. You are absolutely correct. Not only does adding a plate to the bottom flange increase capacity, but installation is a lot easier than adding a web plate.

@bones206
Thanks for the consideration. My plan was to weld the full length and not stitch weld the plate. Also, yes, sidesway buckling checks out.
 
Do you gain capacity laterally bracing the top flange? That is likely the cheapest, since you can have a W shape turned 90 degrees spanning 18', with braces to the top flange at 1/2 or 1/3 points, instead of 18' of welding.

The intermediate stiffeners will have no impact on the utilization ratios you posted, and a web doubler is the least efficient way to reinforce this, as others have pointed out.
 
Back in the day when I designed overhead cranes and runways, the channel was assumed to take the full lateral load. I wonder why the owner want the UC to be 0.85? Your approach seems to be viable. However, keep in mind that the DL from stiffening the runway add more more stress.

bones206, I am not sure whey you need continuous welds vs intermittent? I bet you the cap channel is intermittently welded to the top flange. That is the industry practice. Just ensure that the weld can handle the horizontal shear flow/capacity between the flange and the channel.

Regards,
Lutfi
 
Stitch welds have poor fatigue performance characteristics. Since this beam will be subject to cyclic loading at relatively high stress levels, it would be prudent to go with a continuous weld in my opinion.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor