Hey all
I am trying to figure out how to make a calendar for 9/80 work schedule. I am using MS Project 2007 standard edition.
The work week would be as such - week 1 Monday thru Thursdays 9 hrs/day with Friday at 8 hrs. Week 2 Monday thru Thursday 9hrs/day with that Friday off. Just need for figure how to get Fridays set. Just started using 2007 for just a couple of weeks. Calendar setup is somewhat different from 2003. Just bought a Bible(Elaine Marmel)but still scanning it. Thanks in advance for any help.
Bob
 
Replies continue below

Recommended for you

With the new calendar set up you will need to do each Friday individually - because you are doing every other Friday there are not global set up options. there are only global set ups for time off - not time on.
 