USER10
Materials
- Oct 12, 2007
- 17
In CSAZ662 Commentary part it is stated " it is common industry practice to use –5 °C
as the minimum design temperature for buried piping and either –30 °C or –45 °C (depending on the
local climate) as the minimum design temperature for above-ground piping" .
I think that this practice is not safe as minimum temperature of buried pipes in many northern cities can be much lower than -5°C.
I called a pipeline eng friend who works mostly in projects in Alberta and Northern British Columbia but not in the arctic zone to discuss the above commentary. He stated that in cold cities (where temperature of ground at 3 ft deep is expected to be lower than -5 °C) he just just ordered pipes with proven notch-toughness at -45 °C as most suppliers have already these pipes. In other words, he does not usually bother to determine the minimum design temperature for a specific area for buried pipes and further to carry out proven notch toughness tests at such temperature. My question : is that a good practice...? and what are the implications (e.g cost, materials, pipe performance) of using pipe with proven notch toughness at –45 °C while real minimum temperature could be much lower than that (maybe two or three times lower than -45 °C)>?
Thanks in advance for your thoughts on this subject
as the minimum design temperature for buried piping and either –30 °C or –45 °C (depending on the
local climate) as the minimum design temperature for above-ground piping" .
I think that this practice is not safe as minimum temperature of buried pipes in many northern cities can be much lower than -5°C.
I called a pipeline eng friend who works mostly in projects in Alberta and Northern British Columbia but not in the arctic zone to discuss the above commentary. He stated that in cold cities (where temperature of ground at 3 ft deep is expected to be lower than -5 °C) he just just ordered pipes with proven notch-toughness at -45 °C as most suppliers have already these pipes. In other words, he does not usually bother to determine the minimum design temperature for a specific area for buried pipes and further to carry out proven notch toughness tests at such temperature. My question : is that a good practice...? and what are the implications (e.g cost, materials, pipe performance) of using pipe with proven notch toughness at –45 °C while real minimum temperature could be much lower than that (maybe two or three times lower than -45 °C)>?
Thanks in advance for your thoughts on this subject