vollEngineer
Geotechnical
- Jun 25, 2004
- 44
I have never performed culvert settlement analysis before. I will have (4-foot to 8-foot) box culverts and (36-inch to 54-inch) pipes (RCP and CMP). My predecessor assumed 75%-full culverts and wrote up recommendations to limit settlement to one inch. He/she also neglected wheel loads. It all seems easy enough, but that is what makes me nervous. I am asking for lessons learned, if anyone is willing to provide.