ufcivilengineer
Civil/Environmental
- Jan 2, 2007
- 5
I've been tasked to come up with a life cycle cost analysis spreadsheet for various existing culverts.
Things to consider:
1) Many of these culverts are large diameter CMP
2) Many of these culverts are already at the end of their service life. Internal corrosion. Bituminous Coating gone on 70%-80% of the pipe.
3) Some of the culverts have been compromised structurally, i.e. groundwater can be seen flowing into the culvert through pipe separation.
4) How do I check for voids around the barrel length?
5) Do I replace them. Line them with HDPE?
6) If we line the culvert, do we pump grout into the voids around the existing pipe exterior.
Any input would be greatly appreciated.
Things to consider:
1) Many of these culverts are large diameter CMP
2) Many of these culverts are already at the end of their service life. Internal corrosion. Bituminous Coating gone on 70%-80% of the pipe.
3) Some of the culverts have been compromised structurally, i.e. groundwater can be seen flowing into the culvert through pipe separation.
4) How do I check for voids around the barrel length?
5) Do I replace them. Line them with HDPE?
6) If we line the culvert, do we pump grout into the voids around the existing pipe exterior.
Any input would be greatly appreciated.