Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Custom View

Status
Not open for further replies.

stjuste101

Computer
Sep 25, 2007
28
Hey everyone,

Hope you guys can help me with this. I'm looking to create two views. One view is to show me the following:

Resource name Week 1 Week 2 week 3
Day 1,2,3 Day 1,2,3 etc.

-Resource #1 ---Project (P) name 1--- ---P 2--- etc-
-Resource #2 ------P Name 1---- P Name 2 -------
-Resource #3
-Resource #4

View #2

Project Name Week 1 Week 2 Week 3
-task 1 ------Resource Name----
-task 2


Any help would be greatly appreciated. My job is dependent on this.

Thanks in advance

 
Replies continue below

Recommended for you

I am making the assumption you are working with a master project that contains inserted project schedules.

View #1:
This can be achieved through the Resource Usage View
1. Click on >View, >Resource Usage
2. Insert the column called Project
3. Adjust your timescale accordingly

View #2:
This can be achieved through the Task Usage View
1. Click on >View, >Task Usage
2. Insert the column called Project
3. Adjust your timescale accordingly
4. You will then want to Group by Project - >Project, >Group by, >Customize Group by, >Project, OK

Hope this helps!
J Black
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor