Eng822
Mechanical
- Aug 19, 2015
- 6
Lets say there was a vessel that was designed back before I was born and the code calculation specified a 2500# flange but referenced dimensions for a 1500# flange (basically, there appears to be an error in the design) and the vessel and piping system were built with 1500# flanges. Fast forward several years and now the client wants to replace the vessel but won't accept that they may need to replace their existing piping to match the 2500# flange that should have been there in the first place. The vessel is not installed in the States and their justification is they have never had a problem with the first vessel.
Before it gets mentioned, an app. 2 flange could work but it requires 1-3/4" bolts where the #1500 flange on the existing piping uses 1-5/8" (B7 High strength).
The vessel is to be U stamped. I considered a Div.2 Part 5 approach, but I don't see how FEA could be used to justify the flange since this situation does not fall under U-2(g) and really any form of justification could not be used to say the design is at least as safe as the rules of Div.1.
I have never tried to justify a design based on previous working history so I am asking if anyone knows if there is even an option for that. Destructive testing perhaps but again how is that at least as safe? I think most PV Engineers I talk to have the same understanding that Div.1 is highly conservative less accurate standard so it is not a surprising that the 1500# flanges have worked without any issue. Any experience or opinions on the matter would be appreciated, thank you.
Note: The client is requesting the shell material be upgraded but the flange material matches the existing vessel so it is not an exact copy.
Before it gets mentioned, an app. 2 flange could work but it requires 1-3/4" bolts where the #1500 flange on the existing piping uses 1-5/8" (B7 High strength).
The vessel is to be U stamped. I considered a Div.2 Part 5 approach, but I don't see how FEA could be used to justify the flange since this situation does not fall under U-2(g) and really any form of justification could not be used to say the design is at least as safe as the rules of Div.1.
I have never tried to justify a design based on previous working history so I am asking if anyone knows if there is even an option for that. Destructive testing perhaps but again how is that at least as safe? I think most PV Engineers I talk to have the same understanding that Div.1 is highly conservative less accurate standard so it is not a surprising that the 1500# flanges have worked without any issue. Any experience or opinions on the matter would be appreciated, thank you.
Note: The client is requesting the shell material be upgraded but the flange material matches the existing vessel so it is not an exact copy.