Jefka
Chemical
- Jun 16, 2009
- 21
Let's say there is a control valve with a system upstream designed for 200 psig (i.e. the upstream relief valve set pressure). Operations plans to actually run the upstream equipment at no more than 150 psig.
There's also a a relief valve downstream of the control valve (system downstream design = 50 psig). When sizing this relief valve for a CV fail open case, what does one assume for the CV upstream pressure in these calcs? Would you use:
a.) 150 psig
b.) 200 psig
Assume the client is indecisive and leaving it up to the designer.
There's also a a relief valve downstream of the control valve (system downstream design = 50 psig). When sizing this relief valve for a CV fail open case, what does one assume for the CV upstream pressure in these calcs? Would you use:
a.) 150 psig
b.) 200 psig
Assume the client is indecisive and leaving it up to the designer.