CWI Stamp

Status
Not open for further replies.

marcus001

Industrial
Apr 4, 2009
8
US
Is it necessary for a WPQ Welders Cert to be stamped with a CWI stamp and is it stated anywhere.
 
Replies continue below

Recommended for you

It is necessary only if required by the contract. It is not required by AWS specifications.
 
Then when can we use the stamp

Doesn't hurt anything at all to have a CWI stamp on WPQs, WPSs, PQRs....you can stamp these documents.

 
There is no requirement by AWS to ever use a stamp. Some contracts/job specs will want reports, PQR's, and WPS' to be stamped by a CWI.
 
Makes sense to stamp the WPQ's if you need the WPQ's on future projects. Codes may change, and some clients will only approve WPQ's approved by a third party organization.
 