geomalf
Geotechnical
- Jun 25, 2007
- 2
Hi all
I’m not an expert in specification and construction of the dam, but I got a situation with an existing small dam. The existing dam is an earthfill that is about 140’ x 28’. The height of the dam is approximately 9 feet tall. During the previous repair, the top of the dam was covered with about 18” of concrete. Sheet piles appear to be driven into the ground on the upstream side of the dam, and backfilled with Portland Cement Concrete materials.
The client has asked us to inspect the dam because the locals are concerned about the safety of the dam since water is observed seepage out of the downstream side of the dam. During the construction of the sheet pile structure, a spillway structure was constructed on the upstream of the wall, and is used to direct the flow of the water into downstream
During the field exploration, it is discovered that water leakages are noticed along the edges and crack lines of the existing Portland Cement Concrete cover on the downstream side of the dam. We did some careful drilling at the edges of the dam, and found out that the existing clayey soils are soft and weak (SPT ranges from 0 to 10 within top 20 feet). The other bad sign is that the water levels are not consistent on both edges of the dam; the difference is almost 10 feet. All these findings indicate that the seepage is not consistent, wet and low shear strength of the soil, existing Portland Cement Concrete structure is imeffective
Neither we have the dam construction notes nor the sheet pile information. Apparently, they don’t have it. At first, the client wants to know what’s the situation of the dam, and now they want us to figure some way to repair the dam. I thought of increasing the size of the existing spillway structure, new intake structure, remove the existing Portland Cement Concrete cover to repair the cracks, but I’m not sure whether this addition will work on the existing dam.
Any ideas? Thanks.
I’m not an expert in specification and construction of the dam, but I got a situation with an existing small dam. The existing dam is an earthfill that is about 140’ x 28’. The height of the dam is approximately 9 feet tall. During the previous repair, the top of the dam was covered with about 18” of concrete. Sheet piles appear to be driven into the ground on the upstream side of the dam, and backfilled with Portland Cement Concrete materials.
The client has asked us to inspect the dam because the locals are concerned about the safety of the dam since water is observed seepage out of the downstream side of the dam. During the construction of the sheet pile structure, a spillway structure was constructed on the upstream of the wall, and is used to direct the flow of the water into downstream
During the field exploration, it is discovered that water leakages are noticed along the edges and crack lines of the existing Portland Cement Concrete cover on the downstream side of the dam. We did some careful drilling at the edges of the dam, and found out that the existing clayey soils are soft and weak (SPT ranges from 0 to 10 within top 20 feet). The other bad sign is that the water levels are not consistent on both edges of the dam; the difference is almost 10 feet. All these findings indicate that the seepage is not consistent, wet and low shear strength of the soil, existing Portland Cement Concrete structure is imeffective
Neither we have the dam construction notes nor the sheet pile information. Apparently, they don’t have it. At first, the client wants to know what’s the situation of the dam, and now they want us to figure some way to repair the dam. I thought of increasing the size of the existing spillway structure, new intake structure, remove the existing Portland Cement Concrete cover to repair the cracks, but I’m not sure whether this addition will work on the existing dam.
Any ideas? Thanks.