mmarquardt
Computer
- Jun 12, 2008
- 1
I manage a program-wide deployment schedule where start and finish times are critical. When others pull up my schedule, some see only dates because they have their OPTION-TOOLS-VIEW-DATE FORMAT set to dates only.
Is there an MS Project option or way to force a specific project to display times no matter who pulls it up?
Is there an MS Project option or way to force a specific project to display times no matter who pulls it up?