GerH
Electrical
- Mar 18, 2003
- 48
I am looking into how to estimate if I can energise a large unloaded transformer load, about 50MVA made up of individual 1 to 4MVA units. When the mains fails all the LV loads will be shed throughout the factory.
So far I have been able to test with 16MVA with no problem. The remaining load is no available for test. The running load once energised was about 90kW, 140kVAr. The standby plant is made up of 2.5MVA units and I planned to use the first up.
I also tried enrgising one additiona 4MVA unit and it seemed to create a karger transient volatge dip. Why ?
Any ideas please.
So far I have been able to test with 16MVA with no problem. The remaining load is no available for test. The running load once energised was about 90kW, 140kVAr. The standby plant is made up of 2.5MVA units and I planned to use the first up.
I also tried enrgising one additiona 4MVA unit and it seemed to create a karger transient volatge dip. Why ?
Any ideas please.