ataman
Structural
- Dec 7, 2006
- 53
Hi,
I have a situation with a structure which has three bays of one way spanning structural slabs. One of the end bays has received consistently low compressive strengths based on results (12 MPa) and as such we have instructed the contractor to demolish the slab. The contractor has confirmed that the concrete supplier added several additional gallons of water to the concrete truck for that bay due to a faulty pump and the time that it took them to replace the pump.
Tests indicate that the other two bays are ok. My question is how much of the good slab shoulf be removed as well. If we were doing a construction joint then I would have recommended that the joint fall in the middle third of the slab where the shear is less. Is it unreasonable to ask the contractor to remove this much of the existing slab? Some engineers have advised that I can ask the contractor to demolish from the face of the beam and that the load will be transfered by shear through the reinforcing steel. The bottom steel in several locations does not continue past the beam so I'm wondering if it wise to use it for shear transfer especially since it is a one way slab and the shear as the face of the beam will be the highest.
Thanks in advance for you comments.
I have a situation with a structure which has three bays of one way spanning structural slabs. One of the end bays has received consistently low compressive strengths based on results (12 MPa) and as such we have instructed the contractor to demolish the slab. The contractor has confirmed that the concrete supplier added several additional gallons of water to the concrete truck for that bay due to a faulty pump and the time that it took them to replace the pump.
Tests indicate that the other two bays are ok. My question is how much of the good slab shoulf be removed as well. If we were doing a construction joint then I would have recommended that the joint fall in the middle third of the slab where the shear is less. Is it unreasonable to ask the contractor to remove this much of the existing slab? Some engineers have advised that I can ask the contractor to demolish from the face of the beam and that the load will be transfered by shear through the reinforcing steel. The bottom steel in several locations does not continue past the beam so I'm wondering if it wise to use it for shear transfer especially since it is a one way slab and the shear as the face of the beam will be the highest.
Thanks in advance for you comments.