Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations SSS148 on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Definition of Wet Stamp

Status
Not open for further replies.

COstructural

Structural
Jan 21, 2014
5
When a building department says they need four sets of "wet stamped" drawings, what does this mean? I have heard two different revisions: 1. you cannot have a printer generated stamp it must originate from a ink pad stamp and be manually signed but photocopies of these drawings once that is done are fine. 2. you must ink the stamp, and wet sign all four sets of the drawings.

Any clarification would be much appreciated!
 
Replies continue below

Recommended for you

I would assume option #2 but I'd make the call to be sure. Option #1 certainly sounds like a lot less work. Do you guys have digital stamping in Colorado?

The greatest trick that bond stress ever pulled was convincing the world it didn't exist.
 
With both options, prints to be submitted to the building department, not originals, are wet stamped and wet signed. In either case, prints of these documents could be copied for use in the field by the contractor.

It used to be that the originals were wet stamped and signed, and prints of the originals were submitted to the building department. In this, may be the difference the OP os talking about.

Mike McCann, PE, SE (WA)


 
So is wet signed not enough? Up here in Canada the seal itself it applied electronically and then you sign it after printing.
 
i think the signatures are the important part ... original, not copied.

if the "stamp" was included as part of the doc, I can't see that being that much of a problem (it's more that we can do that these days with the s/ware, as opposed to being impractical in the olde days).

another day in paradise, or is paradise one day closer ?
 
I would just call them to clarify.
In one sense these city jurisdiction personnel are in control as they hold the permitting power.

However, technically, in the US, the signing and sealing of drawings is controlled by the state engineering laws and the state boards, not the cities.
So if cities make you do something not required by the state, you can argue to the city that they are wrong....but the hassle usually isn't worth it.



Check out Eng-Tips Forum's Policies here:
faq731-376
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor