BuilditBob
Specifier/Regulator
- Dec 18, 2006
- 3
I have a question about logistics and risk management with regards to demolition of a heavy industrial building in an urban setting.
We are about to demolish a 5-story reinforced concrete structure in an urban setting. It was once a factory building, and approx 12 bays on each floor were designed for heavy live loads (10" thick flat slabs with 30" dia. concrete columns and shear caps.
After removing everyting but the concrete structure, the demo contractor proposes to attack the conctete slabs with a hydraulic excavator with a universal processor (concrete cracking jaws) and another with a concrete pulverizer, and yet another with a demolition grapple.
The contractor's Work Plan proposes to work from the bottom up (since access to the top of the building will be logistically difficult. The Plan states:
"The second floor slab will be removed in sections of 200 to 300 square feet between columns followed by the removal of the same quantity of slab directly above the section just removed. Once the section of roof slab has been demolished, slab removal between the next columns will begin. Once roof slab has been removed, exposed column will be demolished, starting from top down."
While I have studied engineering, I am a construction program manager--not a practicing structural engineer. I am acting as the Owner's Rep, and my experience with demolition work is limited. This project appears to be one of the more challenging jobs that this demo contractor has undertaken.
Won't removing the lower slabs destabilize the columns? It sounds spooky to me.
I am concerned and would appreciate any helpful advice from anyone experienced in such matters. We are in the HAZMAT abatement and interior demolition stage. The demolition specs don't require a formal submittal of an engineered demolition plan.
We are about to demolish a 5-story reinforced concrete structure in an urban setting. It was once a factory building, and approx 12 bays on each floor were designed for heavy live loads (10" thick flat slabs with 30" dia. concrete columns and shear caps.
After removing everyting but the concrete structure, the demo contractor proposes to attack the conctete slabs with a hydraulic excavator with a universal processor (concrete cracking jaws) and another with a concrete pulverizer, and yet another with a demolition grapple.
The contractor's Work Plan proposes to work from the bottom up (since access to the top of the building will be logistically difficult. The Plan states:
"The second floor slab will be removed in sections of 200 to 300 square feet between columns followed by the removal of the same quantity of slab directly above the section just removed. Once the section of roof slab has been demolished, slab removal between the next columns will begin. Once roof slab has been removed, exposed column will be demolished, starting from top down."
While I have studied engineering, I am a construction program manager--not a practicing structural engineer. I am acting as the Owner's Rep, and my experience with demolition work is limited. This project appears to be one of the more challenging jobs that this demo contractor has undertaken.
Won't removing the lower slabs destabilize the columns? It sounds spooky to me.
I am concerned and would appreciate any helpful advice from anyone experienced in such matters. We are in the HAZMAT abatement and interior demolition stage. The demolition specs don't require a formal submittal of an engineered demolition plan.