LoneStarEngineer
Structural
- May 4, 2016
- 37
I am working on a demolition and replacement of a concrete slab w/deck for a composite floor system. We are essentially removing the concrete slab along with the deck and all the shear studs.
We will be shoring and reusing the steel beams which will be installed with new studs and new concrete slab w/deck. The largest bays contain 40 foot long girders with beams spaced at 8' o.c.
Some of the concerns that I wanted to discuss with the community are:
1. Pneumatic breakers/Jack hammers are proposed to be used for the demolition of the slab. How would the vibration caused by these effect the steel framing and the connections? As per the cut sheet the lowest vibration level for one of these machines is 6.2 m/s2 with a weight of 96 lbs.
2. If Jackhammers are not recommended for demolition of composite floor system, then what is the best way for demolition without adversely affecting the structural integrity of the steel framing systems.
3. Any suggestions for the demolition analysis of the existing steel framing system?
I have been researching on these topics and have not found much information discussing these issues. I hope this post can lead to some useful contributions for a better understanding of demolition of composite floor systems. Please include any/all useful information from experience or from any publications that you might have come across.
Thank you.
We will be shoring and reusing the steel beams which will be installed with new studs and new concrete slab w/deck. The largest bays contain 40 foot long girders with beams spaced at 8' o.c.
Some of the concerns that I wanted to discuss with the community are:
1. Pneumatic breakers/Jack hammers are proposed to be used for the demolition of the slab. How would the vibration caused by these effect the steel framing and the connections? As per the cut sheet the lowest vibration level for one of these machines is 6.2 m/s2 with a weight of 96 lbs.
2. If Jackhammers are not recommended for demolition of composite floor system, then what is the best way for demolition without adversely affecting the structural integrity of the steel framing systems.
3. Any suggestions for the demolition analysis of the existing steel framing system?
I have been researching on these topics and have not found much information discussing these issues. I hope this post can lead to some useful contributions for a better understanding of demolition of composite floor systems. Please include any/all useful information from experience or from any publications that you might have come across.
Thank you.