Hi,
I just finished the design of drilled shafts for a bridge. A utility company expects to excavate a maximum of 11', sometime after the shafts are constructed. They would like to know how close to the shaft they can excavate without undermining the stability of the shaft. Does anyone know of any references, papers or existing standards I could use? The bridge will be built in New Jersey.
The shaft is about 30' deep, and socketed a depth of about 8' into bedrock. The lateral loads control the design.
Thanks.
I just finished the design of drilled shafts for a bridge. A utility company expects to excavate a maximum of 11', sometime after the shafts are constructed. They would like to know how close to the shaft they can excavate without undermining the stability of the shaft. Does anyone know of any references, papers or existing standards I could use? The bridge will be built in New Jersey.
The shaft is about 30' deep, and socketed a depth of about 8' into bedrock. The lateral loads control the design.
Thanks.