KootK
Structural
- Oct 16, 2001
- 18,382
I'm designing my first ever elevator shaft where the shaft will be a stand alone element not really integrated into the building. It will be quite similar in concept to the photo below. I have some questions:
1) For these kinds of elevators, is it normal to have them tied into the second floor? Or are they truly free standing and have an expansion joint at the second level door? Tying into the second floor certainly would help matters structurally but would require connections that pass through the glass. But then the L2 elevation seems as though it would be a natural place for a glass joint (elevator door sill).
2) What kind of drift limitation would apply here? Elevator shafts integral with buildings obviously are designed for h/500 typically so I would consider that to be an upper bound. Could I relax that some?
3) From a stability standpoint, I see the situation as I've shown it in the sketch below. The elevator cab is essentially a concentrated mass that needs to be stabilized by the shaft framing. I would estimate these stability load and then add them to the seismic rail loads provided by the elevator supplier. Is that reasonable?
4) What should I do about the hoist beam? Many of the examples that I've found online have roof framing. However, that may just be to support a glass roof. Could the hoist beam be a roof beam of the main structure above? Or would that be unsafe? Could the hoist beam be a temporary thing used just for the install and stored elsewhere? If I design a permanent hoist beam into the shaft framing, should I expect it to get beat up pretty good during the installation?
Naturally, any advice in addition to these questions would be welcome. For what it's worth, there is an elevator consultant involved in the project. Unfortunately, their ability to advise me has proven quite limited for a number of reasons, not least of which is the fact that the elevators are to be a tenant improvement item in the future.
I like to debate structural engineering theory -- a lot. If I challenge you on something, know that I'm doing so because I respect your opinion enough to either change it or adopt it.
1) For these kinds of elevators, is it normal to have them tied into the second floor? Or are they truly free standing and have an expansion joint at the second level door? Tying into the second floor certainly would help matters structurally but would require connections that pass through the glass. But then the L2 elevation seems as though it would be a natural place for a glass joint (elevator door sill).
2) What kind of drift limitation would apply here? Elevator shafts integral with buildings obviously are designed for h/500 typically so I would consider that to be an upper bound. Could I relax that some?
3) From a stability standpoint, I see the situation as I've shown it in the sketch below. The elevator cab is essentially a concentrated mass that needs to be stabilized by the shaft framing. I would estimate these stability load and then add them to the seismic rail loads provided by the elevator supplier. Is that reasonable?
4) What should I do about the hoist beam? Many of the examples that I've found online have roof framing. However, that may just be to support a glass roof. Could the hoist beam be a roof beam of the main structure above? Or would that be unsafe? Could the hoist beam be a temporary thing used just for the install and stored elsewhere? If I design a permanent hoist beam into the shaft framing, should I expect it to get beat up pretty good during the installation?
Naturally, any advice in addition to these questions would be welcome. For what it's worth, there is an elevator consultant involved in the project. Unfortunately, their ability to advise me has proven quite limited for a number of reasons, not least of which is the fact that the elevators are to be a tenant improvement item in the future.

I like to debate structural engineering theory -- a lot. If I challenge you on something, know that I'm doing so because I respect your opinion enough to either change it or adopt it.