laxmikant07
Mechanical
- Oct 16, 2012
- 8
Dear Sirs,
How we decided drain & air vent piping design pressure & temperature after 2nd isolation valve for boiler proper & non boiler external piping as per ASME B31.1?
As in my case we planned to collect all drains & vents in common drain & vent collectors. Please advice how to decide design parameters after 2nd isolation valve to common collectors.
How we decided drain & air vent piping design pressure & temperature after 2nd isolation valve for boiler proper & non boiler external piping as per ASME B31.1?
As in my case we planned to collect all drains & vents in common drain & vent collectors. Please advice how to decide design parameters after 2nd isolation valve to common collectors.