Need your help guys again!
I am supposed to prepare preliminary design for treating municipal wastewater for two neighboring villages. The issue is that there is a large difference in population throughout the year, due to the tourist season (summer). The first village has 350 permanent residents. During the summer there is additional 5000 people (total 5500 PE). The second village has 320 permanent residents, and additional 950 people in summer (total 1500 PE). The Investors' wish is to have compact, easy to operate and maintain, underground WWTP or WWTPs. As far as I see it, there are couple of possibilities:
1) One centralized WWTP, 7000 population equivalent (PE).
2) Two separate WWTPs, for each village, first 5500 PE, second 1500 PE.
3) 4 separate WWTPs, two for permanent residents in both villages (350 PE and 320 PE), that would work throughout the year, and two for tourists that would work only in summer (5000 PE and 950 PE).
Question: referring to possibility 3: Is it possible for a WWTP to be in some kind of a stand-by regime when tourists are not present? How easy is it to establish biological process again? I guess that activated sludge from other WWTPs could be used to start the process.
As usual, I would be grateful for your suggestions and advices.
Thank you
I am supposed to prepare preliminary design for treating municipal wastewater for two neighboring villages. The issue is that there is a large difference in population throughout the year, due to the tourist season (summer). The first village has 350 permanent residents. During the summer there is additional 5000 people (total 5500 PE). The second village has 320 permanent residents, and additional 950 people in summer (total 1500 PE). The Investors' wish is to have compact, easy to operate and maintain, underground WWTP or WWTPs. As far as I see it, there are couple of possibilities:
1) One centralized WWTP, 7000 population equivalent (PE).
2) Two separate WWTPs, for each village, first 5500 PE, second 1500 PE.
3) 4 separate WWTPs, two for permanent residents in both villages (350 PE and 320 PE), that would work throughout the year, and two for tourists that would work only in summer (5000 PE and 950 PE).
Question: referring to possibility 3: Is it possible for a WWTP to be in some kind of a stand-by regime when tourists are not present? How easy is it to establish biological process again? I guess that activated sludge from other WWTPs could be used to start the process.
As usual, I would be grateful for your suggestions and advices.
Thank you