Rabbit12
Structural
- Jul 23, 2014
- 477
Have a project where we will need to excavate a large amount of rock to build some tanks. We have a preliminary geotech report that gives us an RQD (varies from 73% up to 100%), and an unconfined compressive strength (279 psi). This is claystone.
From those values any way to determine effort required for excavation? Can this stuff be ripped, require a hoe ram, or is blasting a must?
We are in the very early stages of design and haven't contracted for geotechnical for design yet. The current report was done for a different consultant and we just have a copy.
From those values any way to determine effort required for excavation? Can this stuff be ripped, require a hoe ram, or is blasting a must?
We are in the very early stages of design and haven't contracted for geotechnical for design yet. The current report was done for a different consultant and we just have a copy.