Omitting consideration of any code:
With the usual practices here (relatively deep footings) they are quite rigid and it may be the case that not only the actual capacity in flexural-tension exceeds that allowed by the added reinforcement, but the one when considering just the flexural strength allowed by the code also is of bigger capacity than that of the added steel, i.e., once the footing cracks in flexural tension the capacity of steel present (even if one meeting code requirements) is unable to prevent crack failure.
I understand the rebar working with the concrete whilst uncracked and then suddenly both attaining a state that cause the collapse of both. So for these cases rebar is just waste.
I once produced a worksheet to design footings of minimum volume for a set of loads that at service level would respect cracking strenght, then reinforced for factored loads and other requirements and found some were in the case above.
One footing of such design should NEVER crack for the LOADS never SHOULD attain the service level. Again, many cover requirements could be relaxed on that standing.
Respect your question, for strut and tie footings, i.e., rigid ones, it is a rationale of the same that the compressive strut must be contained and hence beyond point of lower support hook development able to anchor the force is required. But, curiously, being thick footings, you may be in one of the cases above, even generous rebar may be unable to enhance capacity above that of first cracking, given the stupendous flexural capacity of a tall footing section. Then the rebar would be, again, waste, and given this, its need of having hooks, forfeited. Yes, the section at the rebar, with just the strut and tie mechanism would ensure safety at the factored level, but you may find the flexural requirement stays under the flexural capacity of just the concrete.
For slender footings, the general requirement applies. But anchoring some rebar force just requires that at both sides of the point, enough length of rebar (with the required safety factors and mandatory minimums) be provided to anchor the load in bond. Omitting the minimums, at the end of a bar in some footing, the stress in the rebar is near nil, hence the theoretical requirement of development there is also nil (conservatively forfeited by any mandatory minimum development lengths). Towards the center of the footing, the required development length can be both bigger than the distance of the point to the end of the bar or more than enough; that would dictate the need of development beyond the end in plan out of the state at that point.
Not to forget that has been accepted practice (here) to use welded meshes that anchor the forces by the transverse rebar (one to the other), so it must be quite general the typical situations of uniform meshes having reserve of strength in general to provide the anchoring forces in shear-friction or confinement ways, or, if you want, as proceeds from the stresses actually resulting from 3D solid analyses.