jlee2752
Structural
- Feb 9, 2024
- 3
I am preliminarily planning the connection for a new culvert extension on an existing old culvert. The existing culvert lies beneath railway and is a concrete closed bottom footing arch culvert built in the 1940s. Unfortunately, there are no clear drawings of the existing culvert, but the condition would be considered fair. Ideally, the culvert would be replaced, but due to the huge inconvenience of interfering with rail traffic, full replacement is not possible. Therefore, the culvert will be cut back and extended; the existing culvert that is left over will be replaced in a future project. The extension will be off one end of the existing culvert and will be a new concrete box culvert.
Obviously, dowelling is the straightforward solution. However, the current arch culvert has over 80 years of consolidation and settlement; it is unlikely to settle much further. The new culvert will settle much more comparatively. No geotechnical investigation has been done yet; we are in very early stages of planning. The flow through the culvert starts at the existing side and flows into the planned box culvert extension; the box culvert will be hydraulically larger than the existing.
I was thinking that there could be an option to place some sort of material between the two culverts to tolerate some differential settlement, but was not sure if this will cause other issues such as misalignment, fill infiltration or leaking. Not sure if anyone here has worked with anything like this and came up with a good solution. While it is possible to reduce bearing pressures by oversizing the span of the box culvert, I am not sure that this will help much to compensate for over 80 years of differential settlement.
Any ideas are greatly appreciated!
Obviously, dowelling is the straightforward solution. However, the current arch culvert has over 80 years of consolidation and settlement; it is unlikely to settle much further. The new culvert will settle much more comparatively. No geotechnical investigation has been done yet; we are in very early stages of planning. The flow through the culvert starts at the existing side and flows into the planned box culvert extension; the box culvert will be hydraulically larger than the existing.
I was thinking that there could be an option to place some sort of material between the two culverts to tolerate some differential settlement, but was not sure if this will cause other issues such as misalignment, fill infiltration or leaking. Not sure if anyone here has worked with anything like this and came up with a good solution. While it is possible to reduce bearing pressures by oversizing the span of the box culvert, I am not sure that this will help much to compensate for over 80 years of differential settlement.
Any ideas are greatly appreciated!