hocha
Civil/Environmental
- Sep 8, 2009
- 5
I am currently witnessing a leakage test on an 8" DIP. The test requires the contractor to maintain a constant pressure in the line (by adding more water if leakage occurs), and then to measure the total volume of water added over the course of the test.
The first go-a-round, over the course of 4 hours, the pressure in the pipeline increased from 150 PSI to 200 PSI. I pointed out that the pipe was not buried and that the temperature increase was most likely causing the pressure increase. The contractor buried part of the line (but not the entire line, as they have work that requires portions of this trench to remain open) and began the test again today. Less than an hour in, the pressure is still rising (although not as dramatically as before). Without making the contractor fill in the entire trench, is there a way to perform this test properly?
The first go-a-round, over the course of 4 hours, the pressure in the pipeline increased from 150 PSI to 200 PSI. I pointed out that the pipe was not buried and that the temperature increase was most likely causing the pressure increase. The contractor buried part of the line (but not the entire line, as they have work that requires portions of this trench to remain open) and began the test again today. Less than an hour in, the pressure is still rising (although not as dramatically as before). Without making the contractor fill in the entire trench, is there a way to perform this test properly?