Hi,
I have some manually operated switches that are used to activate a large exterior lighting installation.
The switches are in a building that is 800m away from the switchboard that supplies the lights.
My first approach is to install those switches in a panel where they are and run a 16 core control cable from there to the switchboard and have the PLC that will receive those switches as input and figure out which circuits to activaye in that switchboard as well.
The question is would those 800m be any problem? can you please recommend an approriate AWG or mm sq. cross section of each core?
I think this is better than having the PLC with the switches 800m away from the switchboard. In that case the outputs of the PLC would have to be driven 800m.
I have considered using an ehternet switch at the location of the switches and at the location of the switchboard to benefit from an existing data network, but it seems the cost of the switches and the additional PLC required at the second end to decode the message and take action will be more than the cost of the multi-core control cable...
Any hand drawn sketch much appreciated
I have some manually operated switches that are used to activate a large exterior lighting installation.
The switches are in a building that is 800m away from the switchboard that supplies the lights.
My first approach is to install those switches in a panel where they are and run a 16 core control cable from there to the switchboard and have the PLC that will receive those switches as input and figure out which circuits to activaye in that switchboard as well.
The question is would those 800m be any problem? can you please recommend an approriate AWG or mm sq. cross section of each core?
I think this is better than having the PLC with the switches 800m away from the switchboard. In that case the outputs of the PLC would have to be driven 800m.
I have considered using an ehternet switch at the location of the switches and at the location of the switchboard to benefit from an existing data network, but it seems the cost of the switches and the additional PLC required at the second end to decode the message and take action will be more than the cost of the multi-core control cable...
Any hand drawn sketch much appreciated