jswpower
Mechanical
- Apr 23, 2012
- 8
In our 30MW steam turbine vibration monitoring system showing vibration reading more than normal level but within trip limit some times.but it is not showing continuously more than normal level reading but not in regular interval also.but we have checked all electrical connection related to vibration monitoring system,all are ok,even we have separated all earthing connection of vibration monitoring system it is now given separately.but still we cant find out the reason really where it is?whether vibration really there in turbine or electrical problem?if it is there in turbine means why it is not coming continuously?