Syahar1975
Mechanical
- Feb 3, 2011
- 224
Dear experts,
We have a shell plate 23 mm thick Group IV as per API 650.
The vertical joint detail is double bevel. By mistake we have cut to single bevel.
The tank designer suggest to raise a concession request to the client since double bevel on 23 mm plate is a project specification.
As per the approved WPS this vertical to be welded by EGW (electro gas welded) process.
I propose to make a test plate (1 ft long) with the same thickness and material group. Start welding till complete on bevel side. Grinding and make a bevel on the opposite site as per the approved drawing and complete welding on this side. Do visual, RT and other mechanical tests.
If the result is OK then we will apply the same thing on the shell plate i.e. complete welding on bevel side and make bevel on the opposite side then complete welding on this side.
Any comments or other suggestion ?
We have a shell plate 23 mm thick Group IV as per API 650.
The vertical joint detail is double bevel. By mistake we have cut to single bevel.
The tank designer suggest to raise a concession request to the client since double bevel on 23 mm plate is a project specification.
As per the approved WPS this vertical to be welded by EGW (electro gas welded) process.
I propose to make a test plate (1 ft long) with the same thickness and material group. Start welding till complete on bevel side. Grinding and make a bevel on the opposite site as per the approved drawing and complete welding on this side. Do visual, RT and other mechanical tests.
If the result is OK then we will apply the same thing on the shell plate i.e. complete welding on bevel side and make bevel on the opposite side then complete welding on this side.
Any comments or other suggestion ?