Hello! I have a project where the client is the GC & the developer. So, he is asking me to do some value engineering. The project consist of a duplex 3-story building. I have bearing load CMU walls and a CIP structural slab structural system. I have two questions:
1) Would you replace the the 8x16 conc. tie beam with a double bond beam on the exterior walls? According to the shell contractor there are some significant saving by doing that.
2) I have a quite important 8x16 conc beam that connects perpendicularly to my existing 8x16 tie beam. In the event I make the switch to a double bond beam, I would need to connect this beam to the double bond beam. I personally never done something like that. Any thoughts?
Thanks in advance for your time and help!
1) Would you replace the the 8x16 conc. tie beam with a double bond beam on the exterior walls? According to the shell contractor there are some significant saving by doing that.
2) I have a quite important 8x16 conc beam that connects perpendicularly to my existing 8x16 tie beam. In the event I make the switch to a double bond beam, I would need to connect this beam to the double bond beam. I personally never done something like that. Any thoughts?
Thanks in advance for your time and help!