ves39
Aerospace
- Oct 5, 2020
- 4
How do you guys handle assigning drawing numbers and tracking/pushing changes during R&D and prototyping of a new product or part?
How and when are part numbers assigned?
How are parts released when a product or part is actively being designed and changes can be frequent and quite drastic?
I'll use an example I encountered on a project just recently. We're designing an overhead panel that has switches, comm equipment, plumbing, etc. and various components and brackets located on the inside. We have a prototype completed that is 90% of the way there, but there are still a few final components being designed and finalized.
One of these parts was a bracket to hold some hose clamps for the plumbing in the panel. The first drawing of the part got sent out to sheet metal and they started cutting material to make the bracket.
Later in the day, a change was made to give the bracket more adjustability. The holes for mounting the clamps were changed to slots, so they could be moved up and down and accommodate different clamp sizes. The material size wasn't affected, so the sheet metal worker continued on with manufacturing the part.
At the end of the day, a final change was made. The plumbing had a protective conduit added to it, which changed the clamp to an even larger size. The bracket now had to be made wider to accommodate two hoses and the larger clamps. A third drawing was given to sheet metal, but now they had to cut new material because they wouldn't be able to make the part from what they had prepared.
So now there were three different drawings floating around all with the same drawing number. They didn't indicate the version of the part or drawing. We don't do that because changes are so common and frequent. Changes and drawings often get deleted as the design progresses, so we don't really track the evolution in the design of a part and there are times where it's difficult to go back to an earlier version if we end up going down the wrong road.
All of this obviously leads to a lot of wasted time, money, and materials.
I think the bigger issue here is our design and manufacturing process. I think we need to revamp our design process and be more thorough with checking that all requirements are met. We're very trigger happy about sending drawings out early. Many changes can be made in the hours that follow and some of the work may end up getting completely scrapped because of a change in the part. I think we need to take a look in the mirror as an organization.
Anyway, I was looking for some advice on where I could begin to start tackling this problem and maybe getting some advice on how manufacturing and changes are handled during the R&D phase of a project in a well organized company with systems in place.
How and when are part numbers assigned?
How are parts released when a product or part is actively being designed and changes can be frequent and quite drastic?
I'll use an example I encountered on a project just recently. We're designing an overhead panel that has switches, comm equipment, plumbing, etc. and various components and brackets located on the inside. We have a prototype completed that is 90% of the way there, but there are still a few final components being designed and finalized.
One of these parts was a bracket to hold some hose clamps for the plumbing in the panel. The first drawing of the part got sent out to sheet metal and they started cutting material to make the bracket.
Later in the day, a change was made to give the bracket more adjustability. The holes for mounting the clamps were changed to slots, so they could be moved up and down and accommodate different clamp sizes. The material size wasn't affected, so the sheet metal worker continued on with manufacturing the part.
At the end of the day, a final change was made. The plumbing had a protective conduit added to it, which changed the clamp to an even larger size. The bracket now had to be made wider to accommodate two hoses and the larger clamps. A third drawing was given to sheet metal, but now they had to cut new material because they wouldn't be able to make the part from what they had prepared.
So now there were three different drawings floating around all with the same drawing number. They didn't indicate the version of the part or drawing. We don't do that because changes are so common and frequent. Changes and drawings often get deleted as the design progresses, so we don't really track the evolution in the design of a part and there are times where it's difficult to go back to an earlier version if we end up going down the wrong road.
All of this obviously leads to a lot of wasted time, money, and materials.
I think the bigger issue here is our design and manufacturing process. I think we need to revamp our design process and be more thorough with checking that all requirements are met. We're very trigger happy about sending drawings out early. Many changes can be made in the hours that follow and some of the work may end up getting completely scrapped because of a change in the part. I think we need to take a look in the mirror as an organization.
Anyway, I was looking for some advice on where I could begin to start tackling this problem and maybe getting some advice on how manufacturing and changes are handled during the R&D phase of a project in a well organized company with systems in place.