Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Drilled Shaft Design help

Status
Not open for further replies.

PAK_ENG

Civil/Environmental
Jul 20, 2020
10
Hi there. I am new to bridge design and would like some assistance. I am designing a multi column bridge pier with continuous footing supported on drilled shafts. I am using RC Pier and hand calculations in my design. I have designed the cap, columns, and footing and am moving on the drilled shafts. RC Pier does not design drilled shafts with footing, only if they are directly supporting the columns. So I am a little stuck on how to do the drilled shaft design. I am using FHWA-NHI 18-024 Chapter 12 as a guide. I have calculated the loads (Mxx, Mzx, and axial load) at the center of the footing, but how would I resolve the moments to find the Mu at the top of each drilled shaft? Also, any free programs that do drilled shaft design or generate interaction diagrams for circular columns based on AASHTO? Any assistance is appreciated. Thank you!
 
Replies continue below

Recommended for you

Answer to your first question, since you have calculated the total forces from the superstructures, now just distribute the loads using P/A ± My/I, in which A represents the number of drilled shafts, and I is the moment of inertia for the drilled shaft group. I am not aware of programs that perform the task you are looking for, so no comment for that.

Another way to distribute the loads is placing the column reactions on the continuous beam (shaft cap), assuming the drilled shaft as supports, and perform continuous beam analysis to get reactions for each drilled shaft.
 
Thanks for the help, Retired13. I would like to get Pu and Mu values at the top of the drilled shafts to use in an interaction diagram. How do I go from the P, Mxx, and Mzz at the center of the footing to those values? I was using P/A + My/I to calculate the Pu at the top of the drilled shaft, as if I were calculating pile loads. But not sure how to go from transverse and longitudinal moment at center of bottom of footing to the Mu needed at top of drilled shafts. Thanks again!
 
image_qjcvqp.png


Assume the cap is rigid. For each of the outer shafts the loads are:
Fy = Py/4 ± Mzz*d1/Iz
Hx = Px/4; Hz = Pz/4 (Px & Pz are lateral forces along the respective axis, not shown on the graph)
Mx = Mxx/4

Do the same for the inner shafts, replace d1 by d2.
 
So lateral loads and moment at the top of each drilled shaft is just the total moment or total lateral load divided by the number of drilled shafts? How different would the results of the continuous beam analysis mentioned above be? I suppose I will have to do both and compare. Thanks for the help, Retired13!
 
Yes, do both cases. The result from the beam analysis will be affected by the stiffness of the concrete cap, but usually will not control, if only the maximum forces are considered for the drilled shaft design.
 
We (at the DOT bridge design section) typically make the assumption that the soil around the footing provides lateral resistance sufficient to mitigate the shear from the column. Therefore, there is no moment applied to the drilled shafts in a configuration such as yours. The drilled shafts are assumed to carry axial load only. We've checked the lateral soil resistance vs. lateral shear for enough of our footings to convince us that this is a valid assumption for the configurations we use.

Rod Smith, P.E., The artist formerly known as HotRod10
 
Retired13 and BridgeSmith, thanks for your help!
 
If your Mxx moment is large, then you need to think about how the load gets into the pile tops.

The only transfer mechanism is through torsion of the cap. If the cap is relatively thin, then it needs to be designed for this torsion and you need to design to resolve this torsion and get it into the piles.

If the moment is small and the cap is massive, then maybe it's resolved into the soil and the piles are essentially axial only.

 
I think it is essential to look at how the bridge girders are supported on the upper pier, and select proper bearing pad to minimize the contact friction. If can't avoid, you might have to provide double row of piles.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor