dison
Structural
- Nov 13, 2001
- 41
I have placed a few exploratory calls to contractors who install drilled shaft foundations, but I don't have any personal contacts with them and haven't received any info back yet, so I thought someone in the forums might be able to help.
I'm investigating overhead clearances required to install drilled shafts beneath an existing bridge. Some are on land and some are in a river. So, the contractor may use several different methods to construct the shafts. For example, over water, the contractor might use a crane on a barge and permanent casing combined with the slurry method while on land, the contractor will probably use a short upper temporary casing and slurry method with a crane or vehicle-mounted drilling equipment. These are my questions:
1)What is the absolute minimum overhead clearance required to construct a drilled shaft? What is the minimum lateral clearance? What are typical lateral clearances?
2)If only a portion of the new drilled shaft overlaps with the existing superstructure (in plan view), can the shaft still be constructed? How much overlap is OK?
3)What is the associated cost difference having clearance restrictions during construction vs. no clearance restrictions?
Normally, you would just design the drilled shafts to be clear of the existing superstructure and then you'd have no problems, however, the client would like to use a particular "standard" substructure and doesn't know if clearances will be a problem. Oh, and absolutely no removing the existing superstructure before construction.
Thanks in advance! ~dison
I'm investigating overhead clearances required to install drilled shafts beneath an existing bridge. Some are on land and some are in a river. So, the contractor may use several different methods to construct the shafts. For example, over water, the contractor might use a crane on a barge and permanent casing combined with the slurry method while on land, the contractor will probably use a short upper temporary casing and slurry method with a crane or vehicle-mounted drilling equipment. These are my questions:
1)What is the absolute minimum overhead clearance required to construct a drilled shaft? What is the minimum lateral clearance? What are typical lateral clearances?
2)If only a portion of the new drilled shaft overlaps with the existing superstructure (in plan view), can the shaft still be constructed? How much overlap is OK?
3)What is the associated cost difference having clearance restrictions during construction vs. no clearance restrictions?
Normally, you would just design the drilled shafts to be clear of the existing superstructure and then you'd have no problems, however, the client would like to use a particular "standard" substructure and doesn't know if clearances will be a problem. Oh, and absolutely no removing the existing superstructure before construction.
Thanks in advance! ~dison