Good day,
How much time is needed to do the concrete durability tests ? The contractor is telling me 120 days are needed before we can do it. A laboratory guy once told me 28 days is enough.
specs doesnt say much about this subject.
Thank you
How much time is needed to do the concrete durability tests ? The contractor is telling me 120 days are needed before we can do it. A laboratory guy once told me 28 days is enough.
specs doesnt say much about this subject.
Thank you