tq3610
Geotechnical
- Mar 13, 2013
- 39
I'm looking for some input on dynamic load testing of an end-bearing steel pile in hard granite bedrock.
Consider a PDA test was carried out on a steel pile acting in end-bearing (~90% EB, loose granular soil above rock) that results in 1,000 tons ultimate capacity at a given set blow-count. The acheived 1,000 tons capacity is limited by the pile driving stresses (45 ksi for 50 ksi steel). The structural capacity of the pile under static load is higher (say, 1,200 tons based on the IBC allowable load capacity).
If this pile is end-bearing in very hard rock, and the limiting capacity of the pile as deterimined by PDA was the upper limit of driving stresses, then what is the fault in using the ultimate pile capacity of 1,200 tons?
From a practical perspective, if the pile was installed to an ultimate capacity of 1,000 tons based on a set blow count and a limiting driving stress, once the pile has been installed and it is then loaded (statically by the weight of the structure) the increase in load from 1,000 tons to 1,200 tons would seemingly only result in the pile penetrating some very minor amount into the very hard to rock. Maybe the pile is set an additional 1/8 or 1/4-inch into the very hard rock? Understandably the pile couldn't be driven to a capacity of 1,200 tons due to the driving stresses, but application of the structure loads being very different in nature to the pile driving stresses, it seems that this situation would be much underestimating the capacity of the pile. Once the pile is confirmed to be well-set into the hard granite bedrock, loading the pile to the maximum allowed by IBC per allowable stresses seems reasonable.
Thoughts on this? If such a pile were to be tested with a SLT I would expect it would yield a result allowing the 1,200 tons acceptable per the structural capacity of the pile.
Consider a PDA test was carried out on a steel pile acting in end-bearing (~90% EB, loose granular soil above rock) that results in 1,000 tons ultimate capacity at a given set blow-count. The acheived 1,000 tons capacity is limited by the pile driving stresses (45 ksi for 50 ksi steel). The structural capacity of the pile under static load is higher (say, 1,200 tons based on the IBC allowable load capacity).
If this pile is end-bearing in very hard rock, and the limiting capacity of the pile as deterimined by PDA was the upper limit of driving stresses, then what is the fault in using the ultimate pile capacity of 1,200 tons?
From a practical perspective, if the pile was installed to an ultimate capacity of 1,000 tons based on a set blow count and a limiting driving stress, once the pile has been installed and it is then loaded (statically by the weight of the structure) the increase in load from 1,000 tons to 1,200 tons would seemingly only result in the pile penetrating some very minor amount into the very hard to rock. Maybe the pile is set an additional 1/8 or 1/4-inch into the very hard rock? Understandably the pile couldn't be driven to a capacity of 1,200 tons due to the driving stresses, but application of the structure loads being very different in nature to the pile driving stresses, it seems that this situation would be much underestimating the capacity of the pile. Once the pile is confirmed to be well-set into the hard granite bedrock, loading the pile to the maximum allowed by IBC per allowable stresses seems reasonable.
Thoughts on this? If such a pile were to be tested with a SLT I would expect it would yield a result allowing the 1,200 tons acceptable per the structural capacity of the pile.