mcm00048
Electrical
- Aug 31, 2017
- 21
Good Morning,
I am working of a 50 MW PV Plant earthing design. PV Plant is connected through 30kV MV Cables to the substation, with in total of 3 circuits. The substation voltage level is 30/220kV and this substation is located 7 km away from PV Plant, this is , that MV evacuation is around 7.2kV underground.
When analyzing the earthing system, I do not know if I should connect earthing grids of PV Plant and substation with 35/50mm2 bare copper cable when both substation and PV Plants are not close to each other, they are separated arounf 7 kilometers. I have found that some other designers connect the PV plant earthing grid with the substation through screens of MV evacuation underground cables. It would be possible?
I have found that IEEE 2778 is related to earthing of PV Systems, does it explain this case?
Could anybody put some light into it?
Thank you.
I am working of a 50 MW PV Plant earthing design. PV Plant is connected through 30kV MV Cables to the substation, with in total of 3 circuits. The substation voltage level is 30/220kV and this substation is located 7 km away from PV Plant, this is , that MV evacuation is around 7.2kV underground.
When analyzing the earthing system, I do not know if I should connect earthing grids of PV Plant and substation with 35/50mm2 bare copper cable when both substation and PV Plants are not close to each other, they are separated arounf 7 kilometers. I have found that some other designers connect the PV plant earthing grid with the substation through screens of MV evacuation underground cables. It would be possible?
I have found that IEEE 2778 is related to earthing of PV Systems, does it explain this case?
Could anybody put some light into it?
Thank you.