AnimusVox
Structural
- Jun 17, 2015
- 45
Hey everyone,
So I just got pulled into this project pretty late and there's some drama going on with the foundations (drama + foundations = uh oh)
The geotech report states there's a bunch of fat clays, silty soils and generally expansive and unwieldy soil at our site, and recommended one of two foundation systems.
The first is the very conventional shallow spread footings, but doing so would require a gratuitous amount of over-excavation and backfill from soil not found on site.
The second option is to use 18' piles.
We requested which would be more cost effective for our client, and the geotech claimed they would not perform any rough estimate because it's outside of their scope and would be more along the responsibilities of the GC, which is understandable.
My question, is when you are provided an option between foundation systems, what are your decisions on a specific foundation system based on?
Thanks!
So I just got pulled into this project pretty late and there's some drama going on with the foundations (drama + foundations = uh oh)
The geotech report states there's a bunch of fat clays, silty soils and generally expansive and unwieldy soil at our site, and recommended one of two foundation systems.
The first is the very conventional shallow spread footings, but doing so would require a gratuitous amount of over-excavation and backfill from soil not found on site.
The second option is to use 18' piles.
We requested which would be more cost effective for our client, and the geotech claimed they would not perform any rough estimate because it's outside of their scope and would be more along the responsibilities of the GC, which is understandable.
My question, is when you are provided an option between foundation systems, what are your decisions on a specific foundation system based on?
Thanks!