I'm hoping someone can shed some light on this.
We currently have weld procedures qualified in accordance with EEMUA 158 and approved by DNV. As part of 158 the wire feed speed is an essential variable but our WPS’s and PQR’s have columns for WFS but they have not been recorded.
What I would like to know is is there a calculation to work out the WFS governed from Amps and Volts and wire diameter?
Any help would be greatly appreciated..