NickParker
Electrical
- Sep 1, 2017
- 434
How do you manage when the mechanical equipments are not finalized early in the project as it happens in every other project. There would be frequent changes in the electrical power requirement of the loads until the mechanical capacity of the loads are finalized.
1. The Electrical team could not exactly estimate the total load in the plant
2. Cannot arrive at the size of the transformer.
3. Cannot select the exact cable sizes.
So on & on
All of which delays the ordering materials/panels etc, which inturn delays the project completion. Yes, we would add some margin and approximately we can arrive at, but still many reworks are required after the final selection of mechanical loads.
Expert experiences / approach in this situation are welcome!
1. The Electrical team could not exactly estimate the total load in the plant
2. Cannot arrive at the size of the transformer.
3. Cannot select the exact cable sizes.
So on & on
All of which delays the ordering materials/panels etc, which inturn delays the project completion. Yes, we would add some margin and approximately we can arrive at, but still many reworks are required after the final selection of mechanical loads.
Expert experiences / approach in this situation are welcome!